Develop Design 5/21/07 5/25/07
Present Design 5/28/07  
Not available 5/29/07 6/5/07
Refine Design 6/5/07 6/22/07
Not available 6/25/07 7/2/07
Final materials due 7/2/07  
Complete design 7/2/07 7/6/07
Final Proofing 7/9/07 7/11/07
Prepare for Printing 7/12/07 7/16/07
Print / Mail house 7/16/07 7/20/07
Mailing 7/23/07  