The 22nd Annual San Diego International Conference
on Child and Family Maltreatment - 2008
Project Schedule

The same Project Schedule is shown here in 2 different views. Above, as a timeline, and below as a table.
There are 2 milestones in the schedule that are represented in red:
Milestone #1 - presentation of design concepts by May, 28th, 2007;
and Milestone #2 - submission of final materials by July 7th, 2007.
| Develop Design |
5/21/07 |
5/25/07 |
| Present Design |
5/28/07 |
|
| Not available |
5/29/07 |
6/5/07 |
| Refine Design |
6/5/07 |
6/22/07 |
| Not available |
6/25/07 |
7/2/07 |
| Final materials due |
7/2/07 |
|
| Complete design |
7/2/07 |
7/6/07 |
| Final Proofing |
7/9/07 |
7/11/07 |
| Prepare for Printing |
7/12/07 |
7/16/07 |
| Print / Mail house |
7/16/07 |
7/20/07 |
| Mailing |
7/23/07 |
|
NOTE: The Project Schedule is provided as a guideline for keeping the project on track.